The Transmission Company of Nigeria (TCN) has commissioned a new 300MVA power transformer at its Benin Transmission Substation to boost electricity supply

Here are some key points about the commissioning:

Capacity Increase: The new transformer is one of two 300MVA capacity power transformers delivered to the substation, with the installation of the second transformer set to commence immediately

World Bank Projects: The transformers are part of the ongoing TCN and World Bank projects aimed at increasing transmission capacity nationwide

Improved Power Reliability:  The addition of the new transformers is expected to improve power reliability and availability in the region

Transmission Infrastructure: TCN is committed to continuously investing in transmission infrastructure to meet the growing demand for electricity in Nigeria